Streetcar Progress Update: Feb. 21, 2014
Feb 21, 2014
Streetcar Progress Update: Week Ending Feb. 21, 2014
This week's big thaw came just in time for us to power through the Liberty & Race intersection this weekend!

Through Monday morning, Liberty is detoured around the trackwork site at Race Street...

...while crews work day and night. Here, they're installing rebar in the excavated track slab. (There are two types of rebar that the crew is holding: The bars that run along the track are #7 bars , or 0.875-inch diameter, and the bars running opposite of the track are #4 bars, or 0.5-inch diameter).

For quality control purposes, a Delta Railroad worker uses a calibrated track gauge to ensure we have the proper distance between the rails. This distance is also called the track gauge, and the Cincinnati Streetcar uses standard gauge rail (which means the distance from the inside of one rail to the other is 56.5 inches).

Excavation for the track has nearly reached Washington Park along Race Street. You can see the park in the background!

At Race and Henry streets, crews have been pouring footers for the Maintenance and Operations Facility.
Traffic Alerts
Our sewer renewal project scheduled for this week was postponed while Duke finished up its restoration work.
So, the detour of 13th Street at Race now will begin Monday, Feb. 24.
This closure is expected to take 5 days, weather-permitting. A detour will be clearly posted.
Progress This Week
MAIN STREET
- 2nd to 3rd: Water main installation; exploratory digging for utilities
- 4th to 5th: Exploratory digging for utilities
- 9th to Court: Underground gas work
- At 12th: Underground electrical work
WALNUT STREET
- 2nd to 3rd: Water main installation
- 5th to 6th: Water main installation; underground gas work
- 9th to Central Parkway: Telecomm work
12TH STREET
- Main to Vine: Underground gas and electrical work; telecomm work
- Vine to Republic: New sewer installation
RACE STREET
- At Central Parkway: New sewer installation
- At 12th: Pole foundations and conduit for traffic signals
- At 13th: Underground gas work
- 13th to 14th: New sewer installation
- 14th to Green: Trackwork
- Green to Sellew Alley: Trackwork concluded; street restoration
- Glass Alley to Henry: Telecomm work
- At Henry: Underslab plumbing and electrical work, storm detention work and foundations for the Maintenance & Operations Facility
ELM STREET
- 14th to Henry: Pole foundations and conduit for traffic signals
Planned For Next Week
MAIN STREET
- 2nd to 3rd: Water main installation; exploratory digging for utilities
- 4th to 5th: Exploratory digging for utilities
- 9th to Court: Underground gas work
- At 12th Street: Underground electrical work
WALNUT STREET
- 2nd to 3rd: Water main installation
- 5th to Government Place: Water main installation
- 9th to Court: Telecomm work
- At Central Parkway: Underground gas work
12TH STREET
- Main to Vine: Underground gas and electrical work
- Vine to Republic: Pole foundations and conduit for traffic signals; new sewer installation; underground electrical work
- At Race: Underground electrical work
RACE STREET
- At 12th: Underground electrical work; pole foundations and conduit for traffic signals
- 12th to 14th: New sewer installation
- 14th to Liberty: Trackwork
- Liberty to Green: Street restoration
- Green to Glass Alley: Sewer renewal work
- Green to Henry: Telecomm work
- At Henry: Underslab plumbing and electrical work, storm detention work and foundations for the Maintenance & Operations Facility
ELM STREET
- At Liberty: Demolition & concrete work at Stop #8
- Wade to Henry: Pole foundations and conduit for traffic signals