CINCINNATI – Crews have paused rehab work on  Columbia Parkway/U.S. 50 due to rain. All lanes are open today, Friday, Nov. 9, and will remain open into next week. The work zone stretches approximately 1 mile between Delta Avenue and William Howard Taft Road in Columbia Tusculum.

Crews are scheduled to resume with lane closures from 9:00 a.m. to 4:00 p.m.Thursday, Nov. 15.

The parkway will be reduced to one lane each direction starting at 9:00 a.m. Friday, Nov. 16, through 6:00 a.m. Tuesday, Nov. 20.

Multi-lane closures will continue until work wraps up later this month. Closures may be in place during morning and afternoon rush hours, depending on the day and field conditions. 

Updates will be posted here, by email and via social media as work progresses.

An electronic message board is posted near the intersection with Delta to provide lane closure updates to commuters.

Motorists commuting to and from Downtown Cincinnati from the East Side are encouraged to plan ahead, allow extra time and consider alternate routes, as needed.