Streetcar Progress Update: August 3, 2015

Aug 03, 2015

Streetcar Progress Update: August 3, 2015

Intersection of 5th and Main Street to Close for Trackwork This Weekend

The intersection of 5th and Main Streets will be closed from 7:00pm, Friday, August 7 until 7:00 am, Monday, August 10 so crews may install track for the Cincinnati Streetcar. Detours will be posted. 

Be sure to check roadmapcincy.com for details on detours and alternate routes. 

 

Block by Block Construction –August 3-9, 2015

MAIN STREET:

  • At 2ndtesting at TPSS (1 week remaining)
  • 4th to 5th:  Excavation & preparation for track slab, track concrete base work, rail installation (1 week remaining)
  • 6th to 8th:  traffic signal work (2 weeks remaining)
  • 8th to 9thsidewalk and ramp restoration (1 week remaining)
  • Court to 12th:  concrete work at Stop #5 (3 weeks remaining)
  • At 12th:  OCS wires, cross spans, and brackets (1 week remaining)

 

 WALNUT STREET:

  • 2nd to 3rdcrosswalk infill, traffic signal work (2 weeks remaining)
  • 4th to 5th:  sidewalk, ramp, and paver restoration (2 weeks remaining)
  • 9th to Central Parkway:  TPSS testing (1 week remaining)
  • At Central Parkway:  OCS wires, cross spans, and brackets (1 week remaining)

 

RACE STREET:

  • At 12th:  OCS wires, brackets & cross-spans will be installed (1 week remaining)

 

CENTRAL PARKWAY:

  • Vine to Walnut:  OCS wires, brackets & cross-spans will be installed (1 week remaining)

 

PROGRESS LAST WEEK:

walnut sidewalk

Crews finish new sidewalk installation in front of the garage exit on Walnut between 4th and 5th.  

main track

Track installation on Main prepares to cross 4th Street.

Stop 5

On Main at Court, crews construct Station Stop #5.

inspection

Project team and staff from the City's engineering consultant inspect units at the CAF plant in Elmira, NY.  

unit 2

In Elmira, Cincinnati Unit #2 is moved to a new location in the plant.  

 

Share Article: