Streetcar Progress Update: August 10, 2015
Aug 10, 2015
Streetcar Progress Update: August 10, 2015
Transdev Streetcar Operations Team Begins Work in Cincinnati
The Operations and Maintenance team from Transdev, the operator for the Cincinnati Streetcar, began work this week onsite. General Manager John Claflin, Maintenance Manager Scott Archibald, and Transportation/Safety & Security Manager Phil Lind hit the ground running, meeting with the project’s Rail Activation Committee and joining the construction team in a walkthrough of the OTR Loop.
Transdev’s team brings a wealth of streetcar and transit experience, working on rail projects in Houston, TX; Portland, OR; Denver, CO; Raleigh, NC; and New Orleans, LA to name a few. Welcome to Cincinnati, John, Scott, and Phil!
Streetcar Stakeholders Meeting this Wednesday, August 12 at Christ Church
The next monthly Streetcar Stakeholders Meeting will be held this Wednesday, August 12 at 9:00am at Christ Church Cathedral, 318 E. 4th Street. Meetings are open to the public and are a great way to find out what’s happening with construction and what’s coming up this fall.
Block by Block Construction –Aug 10-16, 2015
MAIN STREET:
- 4th to 5th: track concrete base work, rail installation, removal of existing pavement (1 week remaining); OCS foundations (2 weeks remaining)
- 6th to 8th: traffic signal work (2 weeks remaining)
- 8th to 9th: OCS foundations ( 1 week remaining), concrete work at Stop #4 ( 3 weeks remaining)
- 9th to Court: paver restoration (2 weeks)
- Court to 12th: sidewalk and ramp restoration (1 week remaining
- At 12th: OCS wires, cross spans, and brackets (2 weeks remaining)
WALNUT STREET:
- 4th to 5th: paver restoration (1 week remaining)
- At Central Parkway: sidewalk and ramp restoration (1 week remaining)
RACE STREET:
- At 12th & Race: OCS wires, brackets & cross-spans (2 weeks remaining)
- At Central Parkway: OCS wires, brackets & cross-spans (2 weeks remaining)
CENTRAL PARKWAY:
- Vine to Walnut: OCS wires, brackets & cross-spans (2 weeks remaining)
PROGRESS LAST WEEK:
Even Lumenocity had a streetcar feature this past weekend. Click on the image above to view the original photo from the Cincinnati Enquirer. [Photo Credit: The Cincinnati Enquirer/Kareem Elgazzar]
Inside Music Hall, this Lego model of the streetcar was featured as part of the Music Hall model.
The Transdev operations crew joined the design and construction teams for an inspection walkthrough of the OTR Loop.
Crews pour concrete on Main Street between 4th and 5th Streets.