Construction Management Project Update Through Mid April 2017

Mar 27, 2017

 

       

CONSTRUCTION MANAGEMENT PROJECT UPDATE

                     March 27, 2017 – April 9, 2017

 

 

 

 

  1. Eggleston Avenue Shared Use Path

Engineer/Inspector: Sarah Perrino/Dave West

Contractor: Adleta Construction

 

Project Description:

This contract includes construction of a bicycle-pedestrian shared use path; installing new inlets; construction of a segmental wall; relocation of light poles and relocation of an irrigation control box.It also includes parking space removals and additions to an existing parking lot; landscaping including installation of tree lawns and plantings in a traffic island and roadway work including realigned curb returns, new curbs, new curb ramps, new drives, new pavement markings, new traffic control poles and devices, and traffic control signage.

                   Project Completion: 

             June 2017

 

              Community:

      Downtown

 

       Scheduled Activities for 3/27/2017 – 4/9/2017

  • Curb ramp installation
  • Sidepath installation
  • Fence installation
  • New storm inlet installation
  • Traffic signal work at Eggleston and Reedy St

               Maintenance of Traffic update for 3/27/2017 – 4/9/2017

  • Access for emergency vehicles, residents and businesses will be maintained at all times
  • During all non-working hours the streets shall be open and available for the movement of traffic
  • Single lane closure on Eggleston from 7:30am to 5:30pm south of Reedy Street

 

2.  Hillside Avenue at Tyler Street Landslide Stabilization

Engineer/Inspector: Mike Mann/Doug Dornette

Contractor: Ford Development Corp

 

Project Description:

This project includes landslide stabilization west of Tyler Street and involves 61 reinforced drilled piers with 59 plugs.

 

 

Project Completion Date:

June 2017

 

Community:

 Riverside

 

Scheduled Activities for 3/27/2016 – 4/9/2017

  • Finishing curb
  • Restoring pavement on Hillside
  • Start clearing embankment east of Tyler Street

Maintenance of Traffic for 3/27/2016 – 4/9/2017

  • Access for emergency vehicles, residents and businesses will be maintained at all times.
  • During all non-working hours the streets shall be open and available for the movement of traffic.

 

 

3.  Marburg Avenue Bridge

  Engineer/Inspector: Mike Mann/Jay Brielmaier

  Contractor: John R. Jurgensen Co.

 

  Project Description:

  This project replaces the Marburg Avenue bridge over the Norfolk Southern Railroad.         The existing bridge will be removed and replaced.  The 86-year-old bridge connects 

  densely populated residential and commercial areas in Hyde Park and Oakley.

 

   Project Completion Date: 

          October 2017

 

   Community:

   Hyde Park, Oakley

 

   Scheduled Activities for 3/27/2016 – 4/9/2017

  • Continue demolition of bridge
  • Preparing to start installation of soldier pile walls

                Maintenance of Traffic 3/27/2016 – 4/9/2017

  • Access for emergency vehicles, residents and businesses will be maintained at all times.
  • During all non-working hours the streets shall be open and available for the movement of traffic

 

                                 

       4.  West MLK Improvements

              Engineer/Inspector: Don Stiens/Kevin Feldkamp/Dennis Winningham

              Contractor: John R. Jurgensen Co.

 

             Project Description:

 This project consists of 0.83 miles of roadway improvements to West Martin                        

 Luther King Jr. Drive from east of West McMicken Avenue to east of Clifton   

 Avenue, full depth pavement replacement (shift to north and widen), signal   

 upgrades and a 12’ multi-use path.

 

           Project Completion:

                     September 2017

 

                   Community:

                     Corryville        

 

                   Scheduled Activities for 3/27/2017 – 4/92017:

  •   Duke Energy installing new poles on the south side of MLK between Dixmyth and Hopple Street overpass

                   Maintenance of Traffic for 3/27/2017 – 4/9/2017:

  •     Access for emergency vehicles, residents and businesses will be  maintained at all times.
  •     Traffic will be restricted to one lane in each direction

 

 

               

         5.           Northside Arterial Improvements

            Engineer/Inspector: Lisa Rowell/David Padur                                

             Contractor: Prus Construction

 

            Project Description:

            The project involves restructuring Colerain Avenue, Blue Rock and Elmore.  Elmore    

          between Doley-By Pass and Colerain will become a two way traffic street when

          complete.  The listed streets will receive new curbs and sidewalks with a grass strip

          between the curb and walks.  All intersections within the project will receive new signal

          configurations.  The project also includes new asphalt pavement after concrete work is                       complete.

 

          Project Completion:

            May 2017

 

          Community:

            Northside

 

          Scheduled Activities for 3/27/2017 – 4/9/2017:

  • Punch list items

          Maintenance of Traffic for 3/27/2017 – 4/9/2017:

  • Access for emergency vehicles, residents and businesses will be maintained at all times.
  • During all non-working hours the streets shall be open and available for the movement of traffic

 

 

        6.  Ida Street Bridge Phase II

             Engineer/Inspector: Lisa Rowell/Bob Backscheider

             Contractor: Prus Construction

 

              Project Description:

The project involves demolition of dilapidated concrete on the substructure on the               bridge.  The deteriorated areas will be removed and replaced creating a more              substantial life expectancy for the bridge.  After the area receives repairs, the entire   

             bridge will be coated.

 

              Project Completion:

               October 2017

 

              Community:

               Mt. Adams

 

              Scheduled Activities for 3/27/2017 – 4/9/2017:

  • Sounding bridge piers, spandrels and beams
  • Chipping deteriorated areas

              Maintenance of Traffic for 3/27/2017 – 4/9/2017:

  • Access for emergency vehicles, residents and businesses will be maintained at all times.
  • During all non-working hours the streets shall be open and available for the movement of traffic

 

 

 

        7.  Colerain Avenue (SCIP)

              Engineer/Inspector: Lisa Rowell/Brian Hurd

              Contractor: John R. Jurgensen Company

 

         

              Project Description:

 This project involves street rehabilitation on city streets.  Including full depth repairs,                           curb and curb ramps, asphalt surfacing and driveway aprons.  A retaining wall will also           be installed on the project.

 

Project Completion:

September 2017

 

Community:

Mt. Airy, Northside

 

Scheduled Activities for 3/27/2017 – 4/9/2017:

  • Full depth repairs

             Maintenance of Traffic for 3/27/2017 – 4/9/2017:

  • Access for emergency vehicles, residents and businesses will be maintained at all times.
  • During all non-working hours the streets shall be open and available for the movement of traffic