Construction Management Project Update For Mid May 2017
May 08, 2017
CONSTRUCTION MANAGEMENT PROJECT UPDATE
May 7, 2017 – May 20, 2017
- Eggleston Avenue Shared Use Path
Engineer/Inspector: Sarah Perrino/Dave West
Contractor: Adleta Construction
Project Description:
This contract includes construction of a bicycle-pedestrian shared use path; installing new inlets; construction of a segmental wall; relocation of light poles and relocation of an irrigation control box.It also includes parking space removals and additions to an existing parking lot; landscaping including installation of tree lawns and plantings in a traffic island and roadway work including realigned curb returns, new curbs, new curb ramps, new drives, new pavement markings, new traffic control poles and devices, and traffic control signage.
Project Completion:
June 2017
Community:
Downtown
Scheduled Activities for 5/7/2017 – 5/20/2017
- Traffic signal work at Eggleston & Reedy Street
- Fence installation
- Project cleanup
Maintenance of Traffic update for 5/7/2017 – 5/20/2017
- Access for emergency vehicles, residents and businesses will be maintained at all times
- During all non-working hours the streets shall be open and available for the movement of traffic
- Single lane closure on Eggleston from 7:30am to 5:30pm south of Reedy Street
2. Hillside Avenue at Tyler Street Landslide Stabilization
Engineer/Inspector: Mike Mann/Doug Dornette
Contractor: Ford Development Corp
Project Description:
This project includes landslide stabilization west of Tyler Street and involves 61 reinforced drilled piers with 59 plugs.
Project Completion Date:
June 2017
Community:
Riverside
Scheduled Activities for 5/7/2016 – 5/20/2017
- Embankment fill
- Completion of grading
- Begin curb work
- Begin reconstructing of Tyler Street and Hillside Avenue
Maintenance of Traffic for 5/7/2016 – 5/20/2017
- Access for emergency vehicles, residents and businesses will be maintained at all times.
- During all non-working hours the streets shall be open and available for the movement of traffic.
3. Marburg Avenue Bridge
Engineer/Inspector: Mike Mann/Jay Brielmaier
Contractor: John R. Jurgensen Co.
Project Description:
This project replaces the Marburg Avenue bridge over the Norfolk Southern Railroad. The existing bridge will be removed and replaced. The 86-year-old bridge connects
densely populated residential and commercial areas in Hyde Park and Oakley.
Project Completion Date:
October 2017
Community:
Hyde Park, Oakley
Scheduled Activities for 5/7/2016 – 5/20/2017
- Continue construction on the substructure of the bridge
- Continue pouring the footings, walls and piers.
Maintenance of Traffic 5/7/2016 – 5/20/2017
- Access for emergency vehicles, residents and businesses will be maintained at all times.
- During all non-working hours the streets shall be open and available for the movement of traffic
4. West MLK Improvements
Engineer/Inspector: Don Stiens/Kevin Feldkamp/Dennis Winningham
Contractor: John R. Jurgensen Co.
Project Description:
This project consists of 0.83 miles of roadway improvements to West Martin
Luther King Jr. Drive from east of West McMicken Avenue to east of Clifton
Avenue, full depth pavement replacement (shift to north and widen), signal
upgrades and a 12’ multi-use path.
Project Completion:
September 2017
Community:
Corryville
Scheduled Activities for 5/7/2017 – 5/20/2017:
- Duke Energy installing new poles on the south side of MLK between Dixmyth and Hopple Street overpass
Maintenance of Traffic for 5/7/2017 – 5/20/2017:
- Access for emergency vehicles, residents and businesses will be maintained at all times.
- Traffic will be restricted to one lane in each direction
5. Northside Arterial Improvements
Engineer/Inspector: Lisa Rowell/David Padur
Contractor: Prus Construction
Project Description:
The project involves restructuring Colerain Avenue, Blue Rock and Elmore. Elmore
between Dooley-By Pass and Colerain will become a two way traffic street when
complete. The listed streets will receive new curbs and sidewalks with a grass strip
between the curb and walks. All intersections within the project will receive new signal
configurations. The project also includes new asphalt pavement after concrete work is complete.
Project Completion:
May 2017
Community:
Northside
Scheduled Activities for 5/7/2017 – 5/20/2017:
- Punch list items
Maintenance of Traffic for 5/7/2017 – 5/20/2017:
- Access for emergency vehicles, residents and businesses will be maintained at all times.
- During all non-working hours the streets shall be open and available for the movement of traffic
6. Ida Street Bridge Phase II
Engineer/Inspector: Lisa Rowell/Bob Backscheider
Contractor: Prus Construction
Project Description:
The project involves demolition of dilapidated concrete on the substructure on the bridge. The deteriorated areas will be removed and replaced creating a more substantial life expectancy for the bridge. After the area receives repairs, the entire
bridge will be coated.
Project Completion:
October 2017
Community:
Mt. Adams
Scheduled Activities for 5/7/2017 – 5/20/2017:
- Sounding bridge piers, spandrels and beams
- Removing deteriorated areas of concrete on bridge
- Concrete pour on pier, spandrels and beams
Maintenance of Traffic for 5/7/2017 – 5/20/2017:
- Access for emergency vehicles, residents and businesses will be maintained at all times.
- During all non-working hours the streets shall be open and available for the movement of traffic
7. Colerain Avenue (SCIP)
Engineer/Inspector: Lisa Rowell/Brian Hurd
Contractor: John R. Jurgensen Company
Project Description:
This project involves street rehabilitation on city streets. Including full depth repairs, curb and curb ramps, asphalt surfacing and driveway aprons. A retaining wall will also be installed on the project.
Project Completion:
September 2017
Community:
Mt. Airy, Northside
Scheduled Activities for 5/7/2017 – 5/20/2017:
- Concrete curb replacement
- Concrete curb ramp replacement
- Retaining wall installation
Maintenance of Traffic for 5/7/2017 – 5/20/2017:
- Access for emergency vehicles, residents and businesses will be maintained at all times.
- During all non-working hours the streets shall be open and available for the movement of traffic
8. Street Rehab/Construction Services/Prus/2017
Engineer/Inspector: David Krusling/Tony Baker/Bob Herling/Frank Mertz
Contractor: Prus Construction Company
Project Description:
This project includes planning the existing asphalt course as necessary; performing
Partial and full-depth pavement repairs; placing an intermediate course of asphalt
Where necessary; repairing deteriorated curbs; constructing curb ramps, concrete walk
And driveway aprons where necessary; perfoming inlet adsustments; adjusting utility
Castings to grade; resurfacing the entire pavement with asphaltic concrete; performing
The necessary pavement markings work; removing and replacing traffic signage; and
Replacing traffic loop detectors where applicable.
Project Completion:
November 2017
Community:
Evanston and Oakley
Scheduled Activities for 5/7/2017 – 5/20/2017:
- Concrete curb and driveway installations
- Full depth pavement repair
- Partial depth pavement repair
- Grind streets
- Place leveling asphalt course
Maintenance of Traffic for 5/7/2017 – 5/20/2017:
- Access for emergency vehicles, residents, and businesses will be maintained at all times.
- During all non-working hours the streets shall be open and available for the movement of traffic.
9. Street Rehab/Construction Services/Adleta/2017
Engineer/Inspector: Lisa Rowell/Emily Hunley/Nick Schinaman
Contractor: Adleta Inc.
Project Description:
This project involves street rehabilitation on several city streets. Including full depth
Repair, curb and curb ramps, asphalt surfacing and driveway aprons. Casting
Adjustments and pavement rejuvenation will also take place.
Project Completion:
October 2017
Communities:
Carthage, East Westwood, English Woods, Hartwell, North Avondale, Over-The-Rhine, West End
Scheduled Activities for 5/7/2017 – 5/20/2017:
- Full depth repairs
- Milling street and installing asphalt
- Concrete curb installation
- Concrete ramp installation
Maintenance of Traffic for 5/7/2017 – 5/20/2017:
- Access for emergency vehicles, residents, and businesses will be maintained at all times.
- During all non-working hours the streets shall be open and available for the movement of traffic.