Streetcar Progress Update: Dec. 20, 2013

Dec 20, 2013

Streetcar Progress Update: Week Ending Dec. 20, 2013

Happy Holidays from the Cincinnati Streetcar Project Team!

Here’s what’s coming up over the next two weeks:

Thursday, Dec. 26

  • Rail delivery on Elm Street (Findlay to McMicken). Elm Street will be closed from 11am-4pm.

Friday, Dec. 27 & Saturday, Dec. 28

  • Rail installation resumes north of Findlay Market

Monday, Dec. 30

  • Rebar installation resumes on Elm Street, north of Findlay Market.
  • Building wood forms for trackwork resumes north of Findlay Market, with concrete placement expected Jan. 2-3.
  • Work resumes on traffic signals and poles for overhead power.
  • Water main work resumes on Walnut & Main streets.

Thursday, Jan. 2

  • Excavation for trackwork resumes at Findlay & Elm streets. This intersection will be closed for several days.

Also, please be aware that utility work along the route will be gearing back up.

Traffic Alerts

  • As noted above, Elm Street will be closed between Findlay Street and McMicken Avenue from 11am-4pm on Thursday. Dec. 26 for a rail delivery.
  • Prus will be excavating for trackwork at Findlay and Elm streets. The intersection will be closed for several days -- but detours will be clearly posted!