Preliminary Six-Year Plan For Street Improvements

Kennedy Connector
Project Engineer: John Brazina, (513) 352-6249

New roadway connecting Kennedy/Duck Creek intersection to the Madison/Camberwell intersection with new roads to I-71 South and Norwood Lateral. Final design is underway. Construction to begin Spring 2012.


Montana Avenue: Boudinot to Farrell Ave.
Project Engineer: Andrea Henderson (513) 352-6236

An evaluation of alternatives was conducted to improve safety for motorists and pedestrians on Montana Ave.  Montana Ave. will be reconfigured as a three lane section prohibiting on-street parking. Minor widening will be necessary at the intersection of Montana Avenue and Westwood Northern Boulevard to incorporate left turn lanes. There will be slight curb movement at the intersection of Montana Avenue and Harrison Avenue to line up the through lanes. Streetscape work will be performed from Epworth Avenue to Hazelwood Avenue. Signal upgrades will take place at the intersections of Montana Avenue with Boudinot Avenue, Epworth Avenue, Harrison Avenue, Wunder Avenue, Westwood Northern Boulevard and Anaconda Avenue.

Construction will begin in May 2011. 

Project Information and Background: Montana Report


Northside Arterial Project
Project Engineer: Morgan Heilman (513) 352-5285

This project involves roadway, bicycle, and pedestrian improvements along Colerain Avenue (US 27) from I-74 exit ramp to Blue Rock Street; and along Blue Rock Street from Colerain Avenue to Spring Grove Avenue. The project includes intersection improvements to Blue Rock Street and Colerain Avenue, Blue Rock Street and Hamilton Avenue, and Blue Rock Street and Spring Grove Avenue. The project also includes intersection improvements to the Colerain Avenue-Spring Grove Avenue-Elmore Street triangular network.

 

Red Bank Expressway: U.S. 52 to I-71
Project Engineer: Martha Kelly (513- 352-3648) 

U.S. 52 to I-71 - Major study in conjunction with Eastern Corridor Major Investment Study. Planning in partnership with Hamilton County Transportation District, Ohio Department of Transportation.


HAM-US27-6.99 Colerain Avenue from Virginia to Leeper
Project Engineer: John Brazina, (513) 352-6249

Improve the horizontal geometry and widen to standard lane widths. This project is the last piece of the improvements to Colerain Avenue (US 27) north of I-74.

This project will begin construction in the Spring of 2012.


Harrison Ave: Queen City Ave. to Corp Line
Project Engineer: Andrea Henderson, (513) 352-6236

This project extends from the Western Corporation limit, Higee Street, to Queen City Avenue.  The majority of the project consists of street resurfacing and curb repair with the remainder including spot improvements at various safety problem locations.  Construction to begin in 2012.  Click the following link to view project improvements. http://www.cincinnati-oh.gov/harrison/


Dana Avenue - Victory Parkway to I-71
Project Engineer: Morgan Heilman, (513) 352-5285

This project will improve pedestrian access and roadway safety. It will include a sidepath from Victory Parkway to Montgomery road along with a widening to allow left turn lanes. It will also include new sidewalk, curb, trees, medians and a new water main.

This project is currently under construction.

West Martin Luther King Drive Access Improvement Project: Clifton Ave. to McMicken Ave.
Project Engineer: Andrea Henderson, (513) 352-6236

Street Improvement project to improve capacity and safety of area. Preferred alternative design has been chosen Stage 1 is complete. Stage 2 will be completed by the Summer of 2011. For more Information, click here.


Madison Road Improvement Project: Alston St. to Ridge Road
Project Engineer: Andrea Henderson, (513) 352-6236

Improvement project will improve capacity of the Madison/Ridge intersection and improve maneuverability for bus and pedestrian traffic along Madison from Oakley Square to Ridge Road. This project includes a GCWW water main upgrade. This project is currently under construction.


North Bend Road:  Betts Ave. to Hamilton Ave.
Project Engineer: Morgan Heilman, (513) 352-5285

This project is an improvement to widen North Bend to meet standard lane widths and provide full pavement replacement to improve driving conditions. The project will remain within the existing right of way. It will include new curb, sidewalk, and trees and a signal upgrade at Savannah.

Construction is expected to start April 2012.

 Winton Road Rehabilitation - Gray Road to Harbury Drive
Project Manager: Sarah Perrino, (513) 352-3411


This project will include street resurfacing, curb repair and full depth repair where necessary on Winton Road to improve driving conditions. To improve pedestrian and bicycle safety, a sidewalk will be installed on both the west and east sides of Winton Road from Gray to North Bend Road.
This project will begin construction in the Spring of 2013.