Traffic Alerts

Find major traffic impacts due to construction on the Cincinnati Streetcar.

August 22, 2014
Weekend Closure: Court & Walnut

Both sides of Court Street between Vine and Walnut will be closed from 8 p.m. Friday, Aug. 22, until 5 a.m. Monday Aug. 25, 2014 so crews may install track for the Cincinnati Streetcar.

July 28, 2014
Lane Restrictions: Main & 6th

Sixth Street and Main Street will be reduced to two lanes for the next 10 weeks for underground electrical work.

July 14, 2014
Closure: Henry Street

Henry Street between Elm and Race will be closed for about two months beginning at 7 a.m. Monday, July 14.

March 24, 2014
Underground Utility Work Begins On Main

Main Street between Sixth and Court is periodically being reduced to one lane starting this week through October for underground electric work.

October 28, 2013
Gas Main Replacement/Relocation Work In CBD

Starting Monday, Duke Energy's contractor will be doing essential gas main replacement and relocation work on Walnut Street and on Main Street.

September 16, 2013
Elm Street Reduced To 1 Lane
Elm Street Reduced To 1 Lane

Elm Street will be reduced to one lane between 12th and 14th streets beginning Monday, Sept. 16, 2013.