Concrete slab work

Streetcar Progress Update: Week Ending Nov. 22, 2013

Construction of the Cincinnati Streetcar is continuing on schedule, north up Elm Street.

The City's construction schedule with Messer/Prus/Delta sets a goal that they reach Henry & Elm streets by the end of this year.

Currently, trackwork is on pace to meet that goal.

Traffic Alert

This is just a reminder of the notice we sent out last week: The intersection of 12th and Race streets will be closed 7am-5pm Saturday and Sunday.

This is so Duke Energy's contractor can do some underground electrical work.

Progress For This Week:

  • Water main installation started on Main Street between 2nd Street and 4th Street. Work continued on Walnut Street between 7th Street and Central Parkway.
  • Conduit work for traffic signals resumed on Race Street between Liberty and Green streets.
  • New sewer installation continued on Race Street near 13th Street, and started on Race between 14th and Liberty streets.
  • Backfilling for the Maintenance & Operations Facility was completed at Henry and Race streets.
  • Storm sewer work continued on Race Street near Findlay Street.
  • Exploratory digging for utilities continued on Walnut Street between 6th Street and 7th streets. Work started on Walnut Street between 5th and 6th streets.
  • Pavement removal started on Elm Street between Green and Findlay streets.
  • Concrete base work for the track continued on Elm Street between 12th and Green streets. Work started on Elm Street near Green Street.
  • Rail delivery and installation continued on Elm Street near Liberty and Green streets.
  • Replacement of the pavers on the east half of Elm Street between 12th and 14th streets continued.
  • Duke Energy performed underground gas work on Main Street between 4th and 6th streets; on Race Street between Liberty and Green streets; and on Walnut Street between 3rd and 5th streets.
  • Duke also performed underground electrical work on 12th Street near Walnut, Vine, and Race streets.
  • Telecom work took place on Race Street near Liberty and Green streets; on Race Street near 14th and 15th streets; and on Race Street near 12th Street.
  • Business surveys and notifications to residents wrapped up on Elm Street between Elder and Findlay streets.

Planned For Next Week:

  • Water main installation will continue on Main Street between 2nd and 4th streets; and on Walnut Street between 7th Street and Central Parkway.
  • Conduit work for traffic signals will continue on Race Street near Liberty and Green streets. Work will start on Race Street between 14th and 15th streets.
  • New sewer installation will continue on Race Street between 14th and Liberty streets; and on Race Street near 13th Street.
  • Foundation work will start for the Maintenance & Operations Facility at Henry and Race streets.
  • Storm sewer work will continue on Race Street near Findlay Street.
  • Exploratory digging for utilities will continue on Walnut Street between 5th and 7th streets.
  • Existing pavement removal will continue on Elm Street near Elder and Findlay streets. Work will start on Elm Street near Findlay and Henry streets.
  • Concrete base work for the track will continue on Elm Street between 12th and Findlay streets.
  • Rail installation will continue on Elm Street near Liberty and Green streets.
  • Restoration of the roadway on the east half Elm Street between 12th and 14th streets will wrap up.
  • Duke will be doing underground gas work on Main Street between 4th and 6th streets; on Race Street between Liberty and Green streets; and on Walnut Street between 3rd and 5th streets.
  • Duke will also do underground electrical work on 12th Street near Walnut, Vine, and Race streets. The intersection of 12th and Race streets will be closed as noted above.
  • Telecom work will take place on Race Street near Liberty and Green streets; on Race Street near 13th and 14th streets; and on Race Street near Central Parkway.
  • Business surveys and notifications to residents will conclude on Elm Street near Findlay Street and Henry Street.
  • We're keeping good access open to Findlay Market at Elder & Elm streets for Thanksgiving shopping.
    We're keeping good access open to Findlay Market at Elder & Elm streets for Thanksgiving shopping.
  • An antique gas main is replaced on Race Street near Findlay Market.
    An antique gas main is replaced on Race Street near Findlay Market.
  • Workers finish concrete after placing it for the track slab along Elm Street, just south of Liberty Street.
    Workers finish concrete after placing it for the track slab along Elm Street, just south of Liberty Street.
  • Further south, crews prep Elm for reopening to traffic. Pavers on the west half will be done next year.
    Further south, crews prep Elm for reopening to traffic. Pavers on the west half will be done next year.