March 21, 2014
Streetcar Progress Update: March 21, 2014
Streetcar Progress Update: March 21, 2014

With trackwork reaching Central Parkway, about a mile of track has been installed!

March 14, 2014
Streetcar Progress Update: March 14, 2014
Streetcar Progress Update: March 14, 2014

There's been a lot of visible progress this week at Henry and Race streets -- the Maintenance & Operations Facility is starting to rise out of the ground.

March 14, 2014
Streetcar-Related Construction On Race, Walnut Streets

Some streets will be closed at Race Street next week for trackwork and sewer work, and Walnut Street will have overnight closures.

March 12, 2014
Update On Vehicle Manufacturing
Update On Vehicle Manufacturing

Vehicles for the Cincinnati Streetcar are really starting to take shape!

March 11, 2014
Temporary Closure Of Race Street

For rail deliveries, Race Street will be closed for several hours on Tuesday, March 11, 2014.

March 7, 2014
Streetcar Progress Update: March 7, 2014
Streetcar Progress Update: March 7, 2014

Did you know March 2-8, 2014 is National Women in Construction Week?

March 4, 2014
Walnut Street Overnight Closures

During overnight hours, Walnut Street will be closed between 5th and 6th streets on the following dates.

February 28, 2014
Streetcar Progress Update - Feb. 28, 2014

Lots of progress this week, as construction started on our first station stop, plus more trackwork on Race Street, and the foundation work at the MOF site.
 

February 24, 2014
Detour Of 13th At Race Street

13th Street will be closed at Race Street for about 5 days beginning Monday, Feb. 24.

February 21, 2014
Streetcar Progress Update: Feb. 21, 2014
Streetcar Progress Update: Feb. 21, 2014

This week's big thaw came just in time for us to power through the Liberty & Race intersection this weekend!